Our Project – Week 31
2544 days
by Simon Scullion
in House
The days are getting longer here now, and we are excited to see progress once more! The window-sills have been fitted, and the rendering will be finished this week. Suddenly the house feels ‘bigger’!




Our Project – Weeks 26 to 30
2552 days
by Simon Scullion
in House
Things have been pretty much stopped for the last month. We have had the first real hassle of the project, with some difficulties with prices of tiles. I won’t go into details, lets hope we can see some good progress again soon. In the meantime the plaster has been drying out nicely, despite some awful weather. We have also been out choosing flooring and doors, along with the the colour of the external rendering last week…