Archive for August, 2004

Our Project – Weeks 4 & 5

A lot happened during these two weeks, while we were in the south of Spain on holiday. The carcass to contain the concrete was finished, with the iron reinforcing located inside. It was then filled with concrete. A day or two later the wooden casing was removed and the RSJs located. The second set of footings at a higher level for the back of the house were then prepared and laid.
Week 5
Week 5
Week 5

Our Project – Week 3

The reinforced concrete for the footings is laid, the casing removed and the wooden carcass for the garage started.
Week 3
Week 3
Week 3

Our Project – Week 2

The footings are laid out. The wooden casing for the footings is built.
Week 2
Week 2

Go to Top